Logo
   Home  Contact Us
 ProgramsSyllabusPeopleTrainingResearchEventsPlacementQuery                                                 

Image

If It Is Man’s Privilege To Be Independent, It Is Equally Important To Be Interdependent

slideshow

INDUSTRIAL LINKAGE
CIVIL SOCIETY

 SARTHAK DAS TRAINING AT NALCO, ANGUL

 At the beginning of our vocational training  in the second week of May, we are allocated our first site where we are encountered with the installation and testing of bored cast-in-situ pile for anode baking furnace of NALCO, Angul for the smelter expansion project Phase-II.  Before going into the details and exact specification of piling work, we will be discussing about the overall piling performed over here is done by Direct Mud circulation method (DMC method). Initially, a hole is bored by using a barrel (a hollow cylinder) by giving blows from a height of at least 2 mt. After a hole is bored and mud is removed upto a depth of  1mt approximately, the casing is inserted in the hole, which guides the chisel to give perfect blow and also restrict the surface soil from collapsing. Now the chisel; is fitted to the rig and it gives blows into the hole till we get a hard strata. The bentonite slurry is continuously passed into the pile hole so that it prevents the soil from collapsing within. After we get a hard /rocky strata, the reinforcement cage with proper cover blocks is inserted. Then the concrete of proper grade is filled through the trimic pipe, using a funnel. Compaction is done by using a vibrator. The details shall be specified further--
            The work involves construction of 500mm diameter straight shaft RCC bored cast-in-situ piles. The approximate length of pile below the cut-off level varies from 5.0m to 8.0m depending on occurrence of founding strata i.e. weathered /disintegrated rock strata and approximate number of piles are as follows -
             Length of the piles is indicative and may vary as per depth of founding strata to terminate the piles.

Information on sub-soil profile
          The soil layer is a silty sand with gravel and is about 3.0mt thickness. It is followed by very dense silty sand with gravel /weathered and disintegrated sand stone.
          Also the ground water tank was found to be varying from 1.2mt to 3.85mt depth below the Existing Ground Level.

Termination of piles
          500mm diameter bored cast-in-situ RCC. piles is terminated in strata consisting of very dense silty sand, weathered /disintegrated rock deposits at a depth of 5.0mt to 9.0mt below the cut-off level with a minimum of 1000mm embedment inside weathered /disintegrated rock, strata. Incase hard /moderately weathered rock is encountered before the pile is embeded 1000mm inside weathered rock, then

·
                     (i)       Chiselling shall be done for at least two hours with 1.5 MT minimum weight and fall of height of 2.0mt.
·
                     (ii)      Set is established (less than 10mm) for 100 to 200 blows.

Safe load carrying capacity
           
The concrete used is of M20 grade having minimum cement content of 400kg/m3 with maximum water-cement ratio of 0.5. However the EIC may allow marginal adjustment in the w/c ratio to obtain concrete of good workability.

Reinforcement
          Reinforcement is high strength deformed bars of grade Fe 415 conforming to IS 1786(latest revision) and the same is weldable quality.To ensure dense and sound concrete up to cut-off level. Approximate graded level was found to be EL.115.0mt. The segments of a reinforcement project 50 times its diameter above cut-off level. For tremic concreted piles, a sample of drilling fluid is taken from the base of the bore hole in the first few piles and at suitable interval of piles thereafter. Concreting shall not proceed if the density of the fluid exceeds 1250kg/m3. The sand content in the fluid shall not exceed 7%. The cement used shall be ordinary Portland cement
Portland  sand cement conforming to IS:455 or Portland Pozzolana cement conforming to IS:1489. The coarse and fine aggregates for concrete should be chemically inert, hard, strong, dense, durable, clean and free from veins, adherent coatings and of limited porosity. Flaky and elongated pieces are not used. Aggregates should not contain deleterious materials such as iron pyrites, coal, mica, shale or similar laminated materials, clay, alkali, soft fragments, sea shells, organic impurities etc. in such quantities as to affect the strength or durability of concrete. For reinforced concrete, any material which cause corrosion of the reinforcement and aggregates which are chemically reactive with alkalis of cement should not be used. Coarse aggregate is aggregate most of which is retained on 4.75mm IS sieve. Fine aggregate is aggregate most of which passes 4.75mm IS sieve but not more than 10% pass through 150 micron IS sieve. Admixtures such as CICO grade I or puddlo or equivalent is used in concrete.
          The reinforcement should be adequately secured and held in position by metal chairs and spacers. Concrete spacers blocks of the same strength as parent concrete shall be used to ensure correct cover of reinforcement. All the reinforcement bars should be tied to form a rigid cage to prevent displacement before or during concreting. The grade of concrete ranges between, or say matches with M-20 with a minimum cement content of 400kg/m3. The slump of concrete ranges between 100 to 180mm depending on the manner of concreting. The stirrups to the main bars should be tack welded. Care should be taken to ensure bars do not come closer while the cage is lowered down the hole. Proper cover and central placement of reinforcement should be ensure by use of suitable concrete rollers or spacers cast specifically for the purpose. The borehole bottom should be thoroughly cleaned to make it free from sludge or any foreign matter before lowering the reinforcement cage. This is called flushing. Concreting is done by tremic method. The concreting placing shall not proceed if the specific gravity of fluid is near about the bottom of borehole exceeds 1.2. The specific gravity of borehole mud is determined by using a hydrometer. The top of the pile is brought above the cut-off level so as to permit removal of  all laitance and weak concreting before capping and to ensure good and sound concrete at the cut-off level for proper embeded into the pile cap.

 Pile testing
          The head of the test pile should be brought to a proper level and plane surface and with adequate space for proper seating of a jack and dial gauges. The test pile surface should be preferred for testing purposes on expiry of one week after casting the pile. Loading should be applied by the reaction method consisting of an hydraulic jack, centrally against a loaded platform. Supports of the of the platform shall be adequately designed .Special anchor piles or any other special type of anchorage systems should be adequate to ensure that the test shall be at least 25% greater than the maximum jaking force required. Settlement of the pile is recorded by dial gauges suspended from datum bars. Four dial gauses of 0.01mm sensitivity shall be positioned on four corners around the pile. The datum bars should have rigid support of preferably of concrete pillars of steel sections, embeded well into the ground .The supports shall be located more than three times the pile diameter ,subject to a minimum of 1.5m clear way from the pile face and also sufficiently away from from the supports of the loaded platform to avoid any disturbances on these accounts. Movements near the supports near the datum should be avoided when the test is in progress. Load corresponding to settlement specific requirements which is based on the nature and the type of structure .50%of the final load at which the total displacement equals to 10% of the pile diameter in case of uniform diameter piles and 7.5% of bulb diameter in in acse of under reamed piles.
          The next part of our training is  restricted to the road work in the
township of NALCO, Angul i.e. repairing of bitumen road from township gate no. 2  near NH 42 to the existing oxidation pond of NALCO township. The process mainly involves five steps - Preparation of surface for bitumen grouting, Supplying ,laying and grouting of pot holes, 40 mm of premix carpeting, 25 mm of premix carpeting , 6 mm of seat coat. Before going into finest details ,it should be noted that we are discussing about the flexible pavement (i.e. bitumen road) ,which is found to be climate specific. It is almost impossible to construct a bitumen road during the rainy season especially carpeting and barring water Bound Mechadam (WBM), grouting and earth work. Such a sort coming is encountered due to a temperature specific work to be discussed further.   Initially the damped road is repaired by removal of damaged bitumen carpet, process called as grouting. it involves removal of earth/murrom/stone (up to  150 mm ) from the damaged portion of the road and stacking of the lead of  50 mm disposal and leveling with in a lead of 3 km or as per the direction of the engineer in charge, namely Mr. S.K.Panda ,DM (CIVIL), Project expansion. that it matches with the exising road profile. The existing road surface is thoroughly scarified and cleaned if dust, loose materials and other foreign materials with the help of wire, brush ,chisel picks etc. Before lying of bitumen grouting over a tack coat as per  direction. Thus a surface is prepared for bitumen grouting after removal of dismantled WBM ,earth, damaged bitumen carpet, removal of earth murrom, stone loose graits etc. stacking the same with a load of 50 m and the breadth of road being 7.1m approximately. It is observed that the cleaning is carried out in such a manner that stone material is exposed to a depth of 1mm to 2 mm without dislodging the interlocking of the metal. All dust and other materials are thus removed and carried away and dumped at designed places . For tack coat ,the bitumen used is of the grade 80/100 and heated to a temperature of 177 degree Celsius is spread uniformly on the road surface in the respective items.  

Hot mix plants

Mechanical mixes are used for preparation of premix bitumen .The hot mix plant of capacity 6 to 10 TPH is installed at a site in the NALCO township .Stone chips of specified size is thoroughly mixed dry in the mixture of the plant.

                    The binder is heated at a suitable temperature for the grade of bitumen and added to the mixture drum at a specified rate per cubic meter of the stone aggregate and thoroughly mixed till stone chips are completely coated with bitumen.

                     Premix stone chips shall be carried in hydraulic operated tractor of capacity 3 to 4 cubic meter to work size and unload these materials in the hopper of the mechanical paver.

                     A mechanical paver is a machine which provides or feed the premix to the surface of the road with a particular thickness uniformly according to to the height of the plate above the surface .The hopper send the premix to the rear of the paver machine by a revolving arrangement where the plate provide certain thickness to premix.

                   It should be noted that premix has to be immediately transferred from hot mix palbt to the premix of 40 mm thick ,with stone aggregate over tack cote is spread manually mechanical paver to match the required slope and camber of different area and size. After laying of premix rolling shall take place with a road roller of 8 to 10 tonne capacity proceed towards the center longitudinally .

                   Wheels of the roller are continuously moistened to prevent the premix adhering and being picked up.

                   After preliminary rolling and honeycombing ,high spots and depression shall be rectified by adding or removing the premix as per requirement and the surface shall be rolled again for compaction .camber is checked at every stage .

                   Premix shall coat ,mixed in a mechanical mixture should be applied after lying and rolling of the carpeting. Proportion of stone aggregate ,bitumen sand etc is specified later.

                   Traffic may be allowed on the road surface preferably 24 hrs after providing the seal coat. It is the duty of the contractor to provide indicator necessary to prevent traffic movement on the freshly compacted premix. 

Bitumen Premix Carpet

Coarse Aggregate:

          The aggregate consist of crushed stone ,hard ,tough, durable rock of uniform quality and should clean free from excess of dust, flat or elongated pieces ,soft or disintegrated stone clay or deletericious matter.

Sand

          The sand shall consist ofg clean ,hard ,durable uncoated coarse dry particles and shall be free from injurious amount of dust, Soft or flaky particles ,organic matter etc.

Bisnder

          The binder shall be bitumen of penetration 80/100 confirming of IS specification .Bitumen is procured in a sealed drum. 

To sum up ,the following processes are followed with a certain specification:-

·                     Firstly ,grouting is performed for 150 mm. Again bitumen carpeting is done for (63-40 mm) total average thickness being 75 mm.

·                     Supplying lying and grouting of potholes with 40 mm stone aggregate up to avg thickness of tack coat of 80/100  bitumen of approved quality of material at 0.75 kg ig spread per square meter of road surface including rolling with a (8 to 10 T) road roller.

·                     Further we are concerned with laying the 40 mm premix carpeting with the premix being prepared at the hot mix plant installed at the site and manual spreading by using stone aggregate at 5.4 m3 per 100 sq matre (with 60%20 mm down and 40% 12.5mm down aggregate) with bitumen of grade 80/100 of approved quality at 56 kg/m2 for 20 mm down stone aggregate over a tack coat at 0.750kg/m2 of the road surface.

·                     Next process involves the lying of 25 mm thick premier carpeting with the premier being obtained from the hot mix plant  of capacity (6 to0 10 )T PHand manual spreading by using stone aggregate 12.5 mm down at 3.37 m3 per 1000 m2 with a bitumen grade of 80/100 of approved quality at 64 kg of hot bitumen  per m3 of stone aggregate over a tack coat of 0.75 kg/m2 of road surface .

·                     Finally there is the lying of 6  mm thick seal coat by using stone aggregate obtained by 100% passing 6.3 mm sieves at 0.9 m3 per 100 sqm with bitumen of grade 80/100 of approved quality at 98 kg per m3 of stone aggregate over a coat of tack coatat 0.5 kg per m2 of the road surface.
 

COLLEGE MAP  | ALUMNI | QUERY 

 © Copyright College of Engineering and Technology, Bhubaneswar
Techno Campus
Ghatikia, Khandagiri,
Bhubaneswar - 751003
Contact the admin